Work commenced on the second part of the Harberton flood relief scheme on Tuesday 3rd January 2006. On the following pages you will find a series of low-resolution images taken to illustrate the progress of the scheme and the techniques used. Brief comments are given where appropriate. Just a few images appear on each page so anyone using a dial-up connection will not have to wait excessively for each page to load.
Pages up to 38 are currently populated with images (at 9/4/06)
Page contents by date:
Phase 1 |
Phase 2 Page 11 2/2/06 - 4/2/06 Page 12 4/2/06 - 6/2/06 Page 13 7/2/06 - 8/2/06 Page 14 8/2/06 - 9/2/06 Page 15 9/2/06 - 11/2/06 Page 16 11/2/06 - 14/2/06 Page 17 16/2/06 - 20/2/06 Page 18 20/2/06 - 22/2/06 Page 19 23/2/06 - 28/2/06 Page 20 27/2/06 - 28/2/06 |
Phase 3 Page 21 28/2/06 Page 22 1/3/06 Page 23 1/3/06 - 2/3/06 Page 24 2/3/06 Page 25 3/3/06 - 4/3/06 Page 26 6/3/06 - 7/3/06 Page 27 7/3/06 - 8/3/06 Page 28 9/3/06 - 10/3/06 Page 29 13/3/06 - 14/3/06 Page 30 14/3/06 - 15/3/06 |
Phase 4 - Finishing touches
Page 31 15/3/06 - 16/3/06
Page 32 17/3/06 - 20/3/06
Page 33 20/3/06 - 21/3/06
Page 34 22/3/06 - 24/3/06
Page 35 24/3/06
Page 36 28/3/06 - 29/3/06
Page 37 6/4/06
Page 38 8/4/06