2006 Flood Relief Work - Page 11

Home   Flood work index   Page 11   Page 12   Page 13   Page 14   Page 15   Page 16   Page 17   Page 18   Page 19   Page 20

Phase 2 starts in the background, trenching for the pipe to St Clement's Terrace, while block formwork retains newly cast concrete in  curved shape to ensure good water flow at the junction. The blocks will be removed.
2/2/06
The trench heads towards Preston Farm, but that electricity cable in the (suspended) ducting is still in the way. SWEB are due to come soon and divert it.
2/2/06
Meanwhile, at the foot of The Old Forge's garden, one small part at least is looking very neat and tidy.
2/2/06
But out in the road progress is slowed by having to dig down through over 4 feet of concrete to access a manhole. The pneumatic concrete breaker calls for ear defenders!
2/2/06