2006 Flood Relief Work - Page 9

Home   Flood work index   Page 1   Page 2   Page 3   Page 4   Page 5   Page 6   Page 7   Page 8   Page 9   Page 10

All the silt has now been removed from below the 'waterfall' at the ford area, lowering the water by a foot so it's now level with the culvert base. The pumps are running again to divert the stream past the work.
30/1/06
Back at The Old Forge the footings are being laid on the culvert lid for the front garden wall to be rebuilt...
30/1/06
...and the rebuilding of the back garden wall is nearing completion.
30/1/06
Remember the new blue water pipe at the top of Page 8? That's now encased in concrete to protect it when the rest of the concrete is poured (see next page).
31/1/06

Top