2006 Flood Relief Work - Page 14

Home   Flood work index   Page 11   Page 12   Page 13   Page 14   Page 15   Page 16   Page 17   Page 18   Page 19   Page 20

Remember the old brick culvert on the previous page? That was here. It has been removed, along with about 3 feet of solid rock beneath it, and the western stream contents are now flowing through the smaller black twin-wall pipe on into the new system.
8/2/06
But turn round and face towards Preston Farm and you may be able to see in this picture that FIVE pipes are visible, obstructing the path of the workmen. Beneath the orange digger bucket is the main sewer, beside the bucket the black cast-iron water main, above that two generations of BT conduit, and behind the digger arm a smaller BT feed conduit. Add to that the large BT manhole at the top of the picture, and this situation requires a great deal of manual digging - and head scratching! This necessitated a site meeting involving the DCC and SDHC engineers, SWH project manager and the site team. Outcome awaited!
8/2/06
At the opposite end of the works, the new bridge parapet is almost complete and a big stretch of finished tarmac had been laid beyond, ready for re-opening this section of the road as far as the junction reasonably soon.
8/2/06

 

The decision was made: The BT box was blocking the route for the new 600ml pipe and has to go, but it is made of extremely hard, steel-reinforced concrete. With cable-carrying conduit all around it's not a job for the mechanical digger but...
9/2/06

 

...a careful man with a pneumatic drill. Good job Betty's bomb wasn't still in the shed behind the wall!
9/2/06

Top