2006 Flood Relief Work - Page 8

Home   Flood work index   Page 1   Page 2   Page 3   Page 4   Page 5   Page 6   Page 7   Page 8   Page 9   Page 10

Back towards the junction box a replacement surface water drain has been fitted across the covered culvert, meeting the roadside drain pit, and just beyond a new blue water supply pipe has been installed.
27/1/06
General view of the part-demolished bridge, the culvert base meeting the stream bed, the two quiet pumps now pumping the entire stream contents past the work, and the temporary pedestrian walkway over the stream.
27/1/06
The workmen came back on Saturday, built a dam of plastic and building blocks, turned the pumps off and sent the stream back under the remains of the bridge. The water level is about a foot above the base of the culvert.
29/1/06
Possibly discernible in this picture is a grey layer several inches thick sloping up from the bottom left of the work face towards the top of the block wall on the right. Was this the original road surface - before the days of tarmac - when the road just sloped down to a ford before the bridge existed?
29/1/06