2006 Flood Relief Work - Page 2

Home   Flood work index   Page 1   Page 2   Page 3   Page 4   Page 5   Page 6   Page 7   Page 8   Page 9   Page 10

The base of the new culvert extends back towards the road and the block walls start to take shape. The new 'soil' pipe is in place above the old.
11/1/06
This week's mystery objects? No, these are the 60 cm diameter twin-wall pipes to be used between the back of  St Clements Terrace and the junction with the overflow culvert from the ford area, stored in the Playing Field car park above the Parish Hall.
13/1/06
The block walls have been extended and the first few pieces of the reinforced concrete lid are in place. The old pipe crossing the culvert has been removed leaving the new one higher up which will be clear of the lid.
13/1/06
The block walls extend towards the road and backfilling with 20ml aggregate takes place.
13/1/06

Top