The base of the new culvert extends back towards the road
and the block walls start to take shape. The new 'soil' pipe is in place above
the old. 11/1/06 |
|
This week's mystery objects? No, these are the 60 cm
diameter twin-wall pipes to be used between the back of St Clements
Terrace and the junction with the overflow culvert from the ford area,
stored in the Playing Field car park above the Parish Hall. 13/1/06 |
|
The block walls have been extended and the first few
pieces of the reinforced concrete lid are in place. The old pipe crossing
the culvert has been removed leaving the new one higher up which will be
clear of the lid. 13/1/06 |
|
The block walls extend towards the road and backfilling
with 20ml aggregate takes place. 13/1/06 |