2006 Flood Relief Work - Page 31

Home   Flood work index   Page 31   Page 32   Page 33   Page 34   Page 35   Page 36   Page 37   Page 38

The metal roadway is lifted again, back onto a lorry for removal. A pump has been operating today to take the western stream pass this work area where a concrete stream base has been laid between the existing bridge pipe and where the new screen will cover the entrance to the new 600ml pipe, and simply covered with blue polythene to allow the water to flow over it overnight as the noisy pump can't be left running (no silent pump is available).
15/3/06

 

Next day and the pump is running, pumping the stream from Mark's garden, over the new concrete base and into the new pipe and away, while footings have been cast for the walls on both sides and around the end of the new pipe, where a new screen will be fitted, as has been done today at the ford end of the project (see below).
16/3/06
And a small amount of soil is needed by the bridge, where the new specially designed stainless screen has been fitted today.
Views of the old and new screens below.
16/3/06