Saturday morning! The electricity company has already been
and diverted the big cable![]() 4/2/06 |
Back at the bridge/ford, the new bridge wall makes
progress. 4/2/06 |
![]() |
![]() |
Monday morning and the junction box cover complete with
manhole opening has been cast and more concrete covering the culvert has
been filled. 6/2/06 |
Heading off towards Preston Farm it gets more complicated
as existing underground pipes have to be linked in to, and even cross, the
new system to ensure that existing water features are maintained. 6/2/06 |
![]() |
![]() |
Outside Pete's house one workman holds back the remains of
Pete's water pipe while the digger presses on. A pre-formed cap and
manhole for the above inspection pit waits nearby. 6/2/06 |