2006 Flood Relief Work - Page 12

Home   Flood work index   Page 11   Page 12   Page 13   Page 14   Page 15   Page 16   Page 17   Page 18   Page 19   Page 20

Saturday morning! The electricity company has already been and diverted the big cable and the men are building the shuttering ready to to cast the cover on the junction box.
4/2/06
Back at the bridge/ford, the new bridge wall makes progress.
4/2/06
Monday morning and the junction box cover complete with manhole opening has been cast and more concrete covering the culvert has been filled.
6/2/06
Heading off towards Preston Farm it gets more complicated as existing underground pipes have to be linked in to, and even cross, the new system to ensure that existing water features are maintained.
6/2/06
Outside Pete's house one workman holds back the remains of Pete's water pipe while the digger presses on. A pre-formed cap and manhole for the above inspection pit waits nearby.
6/2/06