2006 Flood Relief Work - Page 10

Home   Flood work index   Page 1   Page 2   Page 3   Page 4   Page 5   Page 6   Page 7   Page 8   Page 9   Page 10

Complete encasement in concrete up to the level for the new tarmac.
31/1/06
The old brick-arched bridge is deemed insufficiently strong to risk leaving as is, so a 600-ml twin-wall pipe is laid through it. The blockwork is recessed to allow space for stonework to be built around the pipe end and on up to form a new bridge parapet.
31/1/06
Two days later, the new pipe end is embedded in concrete, the new stone bridge wall is taking shape in the blockwork recess...
2/2/06
...a temporary tarmac roadway has been laid across part of the new concreted-in culvert, and the stream is now being pumped under the old bridge.
2/2/06