2006 Flood Relief Work - Page 26

Home   Flood work index   Page 21   Page 22   Page 23   Page 24   Page 25   Page 26   Page 27   Page 28   Page 29   Page 30

Smiling in the sun: from left to right, SWH project manager Steve with three of the regular Harberton crew since work started just over two months on 3rd January 2006, Mike, Nigel and Len.
6/3/06
The wall at the end of St Clements Terrace gardens is taken down carefully after the ivy has been removed and the stone is saved for the rebuilding work. All this work is done by hand. The stone is simply loaded into the digger bucket to move it out of the way.
6/3/06
The new pipe will head through the gap in the wall and in a line to the left of the end of St Clements Terrace.
6/3/06
Another day, not sunny but wet. Twice the length of wall is down now and the gardens have been prepared for laying a metal trackway, as in the Old Forge garden at the beginning of the project.
7/3/06