Smiling in the sun: from left to right, SWH project
manager Steve with three of the regular Harberton crew since work started
just over two months on 3rd January 2006, Mike, Nigel and Len. 6/3/06 |
|
The wall at the end of St Clements Terrace gardens is
taken down carefully after the ivy has been removed and the stone is saved
for the rebuilding work. All this work is done by hand. The stone is
simply loaded into the digger bucket to move it out of the way. 6/3/06 |
|
The new pipe will head through the gap in the wall and in
a line to the left of the end of St Clements Terrace. 6/3/06 |
|
Another day, not sunny but wet. Twice the length of wall
is down now and the gardens have been prepared for laying a metal trackway,
as in the Old Forge garden at the beginning of the project. 7/3/06 |