The first road closure now takes effect as equipment blocks the road.

A mini dumper truck is lowered into the culvert to transport the lid pieces to the working area.
16/1/06
The point under the road outside The Old Forge where the overflow culvert from the ford will meet the 60cm pipe from St Clements Terrace to flow down into the open stream. The workmen knew where most of the underground services were before they dug, they knew the 12" drain behind the workman's right arm was there, but they didn't know it had nearly 3 feet of concrete on top of it - which had to be carefully removed - with the electricity cable next to it!
17/1/06
The lid of this section is now complete, another new 'soil' pipe has been installed, and the garden awaits restoration...
19/1/06
...while reconstruction of the garden wall commences.
19/1/06