2006 Flood Relief Work - Page 19

Home   Flood work index   Page 11   Page 12   Page 13   Page 14   Page 15   Page 16   Page 17   Page 18   Page 19   Page 20

There's the BT box again, and now the top tarmac layer has been applied to the whole of the bottom road. Although not 'officially re-opened' yet, it was possible to drive through at the end of the day.
23/2/06
2.30pm Friday and the workmen have finished early, not because of P.O.E.T.S. but because they may be called out to salt the local roads tonight - snow is forecast. The bottom road is open while the road up past St Andrews Cottages is most definitely closed. Just behind the 'Road Closed' sign and to the left they've connected up the manhole at the base of the wall (below which is the old western stream) to the new system.
24/2/06
A pair of BT cables - here suspended above the new concrete on the left from the piece of wood - were slightly damaged externally when this connecting trench was excavated.
27/2/06
A BT engineer has repaired both cables.
28/2/06