The second section of culvert base, back from the junction
towards the ford, which will run beneath the road, starts to take shape. 19/1/06 |
|
A further section of base is excavated, carefully around a
selection of further service pipes and cables, and more concrete laid. The
junction box begins its build, with a 10" twin-wall pipe inset for the
roadside surface water drain that previously lay beneath 3 feet of
concrete. 20/1/06 |
|
More of the junction box build, including the first short
section of large diameter pipe that will head for the W end of St Clements
Terrace. 20/1/06 |
|
Turning S from the junction box, the part-covered culvert
is seen heading for the open stream. 20/1/06 |